Major project milestones in August
September 3, 2025
From breaking ground on long-awaited projects to completing critical emergency repairs ahead of schedule, the Texas Department of Transportation (TxDOT) had a landmark month in August, advancing efforts to modernize infrastructure and improve safety across the state.
Cow Creek bridge rebuilt in 29 days
After being washed away by deadly floods over the Fourth of July weekend, the Cow Creek bridge—linking Lago Vista, Marble Falls, and Cedar Park—was rebuilt in just 29 days, well ahead of the original September deadline.
TxDOT awarded a $4 million emergency contract to Hunter Industries, who began work on July 21 and finished construction before the end of August.